Section 5: Preliminary Design Submissions
Anchor: #i1003515Submissions
The preliminary submission should clearly establish the design criteria or guidelines under which the project is being developed. The following table outlines preliminary design items that should be submitted.
|
Item |
Submission |
|---|---|
|
Design Summary Report
|
As soon after project authorization as practical, submit to DES, Field Coordination. |
|
Pavement design |
With copy of typical sections to Pavement Design Section, DES, as soon after project authorization as practical. |
|
Schematic layout |
Submit to DES, Field Coordination prior to initiating detailed plan preparation. |
|
Exhibit layouts for work on railroad rights of way for railroad agreements |
Refer to Traffic Operations Manual, Railroad Operations Volume. |
|
Bridge layouts |
Submit in accordance with the Bridge Project Development Manual. |
|
Hike/Bike facility schematic |
Submit to DES, Field Coordination prior to initiating detailed plan preparation. |