Section 2: Research Cycle Overview
Anchor: #i1003526Timeline
The following chart presents an overview of the research program cycle timeline.
|
Approximate Dates |
Activity (described in more detail in Section 3) |
|---|---|
|
July 1 |
|
|
July 1 – August 7 |
Research needs are identified and developed. |
|
August 1 |
Semi-annual reports (SARs) are due to RTI. |
|
August 7 |
|
|
August 15 |
RTI sends research needs to RMC and TAP chairs for review and/or rewrite. |
|
September 1 |
PD responses on semi-annual reports are due to RTI. |
|
September – October 15 |
TAP meetings are held to review, rewrite, and prioritize project statements. |
|
October 15 |
RTI sends advance meeting materials to RMCs, including project statements. |
|
November – first week |
Research Management Committee (RMC) fall meetings are held. |
|
November – December 15 |
PMCs are formed and project statements are refined. |
|
Early December |
Research Oversight Committee (ROC) meeting is held. |
|
December 15 |
Final project statements from PCs are due to RTI. |
|
December 15 – January 31 |
RTI develops Request for Proposals (RFP). |
|
January 31 |
RTI sends RFP to universities. |
|
February 1 |
RTI requests semi-annual reports. |
|
Mid-February – mid-March |
Optional pre-proposal meetings are held. |
|
February 15 – June 1 |
Optional TAP meetings are held to discuss research needs and LRRPs. |
|
March 1 |
Semi-annual reports are due to RTI. |
|
March 7 |
RTI sends semi-annual reports to PMCs. |
|
March 25 |
University proposals are due to RTI. |
|
April 1 |
|
|
April 1 – May 1 |
PMCs review proposals. |
|
April 22 |
RTI requests modifications from universities. |
|
April 22 – May 7 |
Universities develop modifications. |
|
May 1 |
Proposal selections are due to RTI. |
|
May 7 |
Modifications from universities are due to RTI. |
|
May 21 |
RTI sends advance meeting materials to RMCs. |
|
June – first week |
Research Management Committee (RMC) spring meetings are held. |
|
Early July |
Research Oversight Committee (ROC) meeting is held. |
|
July – August |
|
|
September 1 |
New fiscal year program begins & PDs assume oversight of projects. |