Section 2: Research Cycle Overview

Anchor: #i1003526

Timeline

The following chart presents an overview of the research program cycle timeline.

Anchor: #i1002673Overview of Research Cycle Timeline

Approximate Dates

Activity (described in more detail in Section 3)

July 1

  • RTI requests research needs from D/D/Os, TAPs, and universities.
  • RTI requests semi-annual reports.

July 1 – August 7

Research needs are identified and developed.

August 1

Semi-annual reports (SARs) are due to RTI.

August 7

  • Research needs from D/D/Os, TAPs, and universities are due to RTI.
  • RTI sends semi-annual reports to PMCs.

August 15

RTI sends research needs to RMC and TAP chairs for review and/or rewrite.

September 1

PD responses on semi-annual reports are due to RTI.

September – October 15

TAP meetings are held to review, rewrite, and prioritize project statements.

October 15

RTI sends advance meeting materials to RMCs, including project statements.

November – first week

Research Management Committee (RMC) fall meetings are held.

November – December 15

PMCs are formed and project statements are refined.

Early December

Research Oversight Committee (ROC) meeting is held.

December 15

Final project statements from PCs are due to RTI.

December 15 – January 31

RTI develops Request for Proposals (RFP).

January 31

RTI sends RFP to universities.

February 1

RTI requests semi-annual reports.

Mid-February – mid-March

Optional pre-proposal meetings are held.

February 15 – June 1

Optional TAP meetings are held to discuss research needs and LRRPs.

March 1

Semi-annual reports are due to RTI.

March 7

RTI sends semi-annual reports to PMCs.

March 25

University proposals are due to RTI.

April 1

  • PD responses on semi-annual reports are due to RTI.
  • PD justifications for modifications they support are due to RTI.
  • RTI sends proposal review packages to PMCs.

April 1 – May 1

PMCs review proposals.

April 22

RTI requests modifications from universities.

April 22 – May 7

Universities develop modifications.

May 1

Proposal selections are due to RTI.

May 7

Modifications from universities are due to RTI.

May 21

RTI sends advance meeting materials to RMCs.

June – first week

Research Management Committee (RMC) spring meetings are held.

Early July

Research Oversight Committee (ROC) meeting is held.

July – August

  • RTI finalizes and executes university and in-house project agreements.
  • RTI sends executed project agreements to universities, divisions, and PMCs.

September 1

New fiscal year program begins & PDs assume oversight of projects.