Purpose

The purpose for this revision is align the manual with the passage of HB 2422 in the 86th Texas Legislature and SB507 in the 87th Texas Legislature. Joint Trench Opportunity language was added due to the passing of HB 2422, revising Texas Transportation Code 201.671 to 201.673. The passage of SB507, adding Texas Transportation Code 250.002, allows broadband-only providers to use State right of way at no cost.

Anchor: #RHVQSUWB

Changes

Chapter 1:

    Anchor: #MOFUGCLQ
  • In Section 1 “Utility Adjustment Overview”, updated the table of utility forms. Removed ROW-U-43A, ROW-U-43B, ROW-U-139A, ROW-U-MOU1, ROW-U-MOU2, and added ROW-U-SP2125.

Chapter 5:

    Anchor: #EILMMMKM
  • In Section 1 “Determination of Utility Impacts”, modified the discussion of justification of utility adjustments.
  • Anchor: #KJYMXIUQ
  • Updated Section 3 title from “Utility Engineering Contracts” to “TxDOT Utility Contracts”, and modified text to include the addition of SUE and Utility Coordination Contract information and Utility Accommodation Coordination and Verification (UACV) information.
  • Anchor: #WNSMJNYG
  • Added a new Section 11 “Broadband Initiatives” which discusses joint trench opportunities and the joint duct bank accommodation program.

Chapter 7:

    Anchor: #TEVOBESR
  • Added paragraph to Section 4 “Buy America Guidelines” regarding FHWA steel material manufacturing process requirements.

Chapter 8:

    Anchor: #SDOXEVME
  • Added additional eligibility ratio content to Section 2 “Utility Property Ownership”.

Chapter 9:

    Anchor: #YNAUQLJC
  • Updated Transmittal Memo signature requirements in Section 4 “Agreement Assemblies”.
  • Anchor: #CACOOYJY
  • Added existing easement content to Section 6 “Utility Joint Use and Occupancy”.

Chapter 11:

    Anchor: #LFBKTGJH
  • Updated Section 1 “Invoicing and Payment Procedures”.
  • Anchor: #YXWQNAJE
  • Updated Section 2 “Partial Payments”.
  • Anchor: #XIHTWTVH
  • Moved LPA Final Billing information and requirements from Section 3 “Final Billings” and adding the LPA Final Billing information and requirements to Section 4 “Final Billing for Local Utility Payment (LUP)”.

Appendix B:

Entire manual:

    Anchor: #XUNNBJHR
  • Added TxDOTCONNECT terms “Utility ID”, “Project ID” and “ROW Project ID” throughout the manual
  • Anchor: #SJCLOXHD
  • Made additional text changes throughout manual for clarification.
Anchor: #MDSLOOQY

Note

Some hyperlinks will not work when a PDF version of this manual is downloaded and used offline.

Anchor: #VNTMRYKT

Contact

Gregory Faber, Right of Way Division Utility Portfolio Section Director, 512.987.0994