Anchor: #i1004293

Section 3: Plan Standards

Anchor: #i1004298

Introduction

This section explains some of the standard practices used in TxDOT highway illumination plan layouts.

Anchor: #i1004308

Scale of Plans

Generally, a scale of 1:100 provides plenty of detail for lighting layouts. Underpass lighting sometimes requires 1:50. Other special lighting systems, such as tunnel lighting, may require more detailed layouts.

Anchor: #i1004320

Boring Logs

High mast lighting layouts should include soil boring logs. See the Geotechnical Manual (Bridge Collection) for details.

Anchor: #i1037939

Standard Plan Symbols

TxDOT has developed standard illumination symbols to aid in plan preparation. Figure 6-1 explains these symbols.

Standard symbols for light poles used by
TxDOT in plan preparation. Note that breakaway transformer base
poles are represented by a square, and non-breakaway (or shoe base) poles
are represented by a small circle. (click in image to see full-size image) Anchor: #UISWPDNWgrtop

Figure 6-1. Standard symbols for light poles used by TxDOT in plan preparation. Note that breakaway transformer base poles are represented by a square, and non-breakaway (or shoe base) poles are represented by a small circle.