Chapter 19: Enforcement

Anchor: #i998639

Section 1: Enforcement

If the LG determines the prime contractor has failed to meet the established DBE goal, has not demonstrated good faith efforts, or failed to correct DBE Program deficiencies, the LG will initiate administrative action against the prime contractor in accordance with applicable regulations. Administrative actions may include the following:

The LG will notify the prime contractor in writing of the determination. The notice will include the reasons for the determination and specify the administrative action.