Section 4: Design Phase

Anchor: #i1000952

RR SOW and Traffic Control Plan (TCP)

RRD will send a request to the district for CSJ and associated spreadsheet of projects on the replanking. The district shall upload the CSJ to TRIMS. The district shall also inform RRD the following:

RRD will prepare RR Scope of Work (RR SOW) using the tabulation spreadsheet or Form 1876. If applicable, the district may provide the TCP detailing the signage and possible routes at the crossing. All plan sheets and non-standard TCPs must be signed, sealed, and dated by a licensed professional engineer. If the railroad develops the traffic control plan, then TxDOT Standard TCP sheets may be used as a guide. The railroad shall submit the actual TCP to the district a minimum of 30 days before the closure is planned.

Whenever practical, the highway should be fully closed in both directions for 36 to 48 hours and traffic detoured during construction, allowing the railroad company to replank the entire roadway to reduce construction time and provide a more durable crossing surface. Closing one side at a time, a typical practice on roadway construction projects, is usually not feasible on replanking projects due to issues in matching grades on the crossing surface panels and mobilization of railroad company crews. However, the crossing may be replanked at night or on a weekend in some cases, and this should be noted on the RR SOW. Alternatively, a temporary crossing (shoofly) adjacent to the roadway may be used if the roadway cannot be closed.

Anchor: #i1000977

Railroad Company Approval

RRD will issue a letter to each railroad company with crossings on the Exhibit L and associated crossing data. The railroad companies will review the list and comment on any crossings as necessary. After all comments are resolved, the railroad companies send a signed letter to RRD to:

Anchor: #i1001002

Cost Estimates

If a Master Agreement which includes a provision for lump sum payment does not exist, RRD provides the Exhibit A or RR SOW to the railroad company to produce an estimate for work involved in replanking the crossing.

The district may prepare a cost estimate for labor and materials provided by the district, although this work is not funded through the replanking program.

RRD will review and approve railroad company cost estimates prior to preparing the individual project agreement. For further information on reviewing railroad company cost estimates, see Chapter 2.