Chapter 8: Right of Entry Process

Anchor: #i998876

Section 1: Overview

Anchor: #i998881

Right of Entry Agreement

All Class I and some shortline railroad companies operating in Texas require an agreement with contractors to perform work in the railroad's right of way. One of these agreements is a Right of Entry Agreement. Examples of work that will require a Right of Entry include:

TxDOT is not a signatory party in these Right of Entry Agreements. This is a two-party agreement between the railroad company and an awarded contractor after a C&M or maintenance agreement has been executed by the state and the railroad company. TxDOT has agreed to facilitate Right of Entry Agreements for Union Pacific Railroad. Refer to the Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges, Item 5, Article 8.3 for more information.

If a Right of Entry Agreement is required, the contractor cannot begin work within railroad right of way until a fully executed Right of Entry Agreement is obtained. Information for the railroad requirements for Right of Entry Agreements on each project can be found on the Scope of Work Sheet.

NOTE: Union Pacific Railroad Maintenance Consent Letters with Contractor Endorsement is covered in Chapter 3, Maintenance Projects.

Anchor: #i998951

Process for Obtaining a Right of Entry Agreement

The flow chart depicts the process for obtaining a Right of Entry Agreement on a construction project.

NOTE: Project steps and time frames vary depending on scope of the project.

Right of Entry Agreement Flow Chart  (click in image to see full-size image) Anchor: #AVLDNNSCgrtop

Figure 8-1. Right of Entry Agreement Flow Chart