Chapter 16: Change Orders
Anchor: #i998599Section 1: Overview
Circumstances may arise during construction requiring changes to the scope of the work contained in the contract; these are referred to as change orders. The prime contractor should closely monitor change orders to verify if adjusted items or work will impact DBE subcontracted items. The DBE goal applies to the final value of a contract to include all change orders.
Anchor: #i998609Increases of Scope of Work
If TxDOT issues a change order which increases or adds new work items, the prime contractor must ensure that it has obtained sufficient DBE participation to meet the contract goal on the final contract value or has made good faith efforts to do so.
If the prime contractor determines that additional DBE participation cannot be obtained, the prime contractor shall request a waiver of the participation after submitting documentation of good faith efforts to meet the DBE goal.
Anchor: #i998624Reduction of Scope of Work
If a change order eliminates work designated in a DBE commitment, the prime contractor must follow the termination procedures and must make a good faith effort to meet the DBE goal on the final contract value.