Section 2: DBE Trucking Utilization
Prime contractors will provide to the District a completed DBE Trucking Utilization Form 2660. The form will be submitted to the District after the contract has been executed and will not be submitted with the UP.
In order to complete the form, the prime contractor will request, from the DBE trucking firm, the following:
- Anchor: #YKJNGYSQ
- The number of hours or quantities to be hauled. Anchor: #VKXGUEDD
- The number of fully operational trucks owned by the DBE. Anchor: #JMALYLXB
- The number of leased trucks to be used on the project, with copies of the lease agreements. Anchor: #DLQVLKLY
- The information required for the DBE truck unit listing on Form 2660.
The District will review and approve the form. This review and approval process must be conducted prior to the prime contractor beginning any hauling services being performed for DBE credit.