Anchor: #i1084975

Section 7: Utility Considerations in State Participation 2125 (SP2125) Program

Anchor: #ENMVKPEY

Overview

Reimbursements will be handled in compliance with Chapter 11 Section 2 and 3 if applicable.

Because of the fiscal constraint provided under Transportation Code, Section 203.092(e), the department:

    Anchor: #LFXHMJPR
  1. may prioritize the utility requests based on the needs of the department, including the construction schedules of the projects requiring relocation of utility facilities;
  2. Anchor: #GUQHYXIF
  3. may delay until the next fiscal year the payment of all or part of a claim made by a utility if at the time the claim is received by the department, the payment is prohibited by Section 203.092(e); and
  4. Anchor: #VUVQDDEI
  5. will not pay a claim for payment that is received by the department later than one year after the date that the relocation of the utility facility is completed.