Section 8: Cost Charge for Passes (for State)

Anchor: #i1000376

Procedure

All structures and appurtenant facilities (such as cattle guards) required for passes provided in the right of way transaction will be handled in the construction project as a construction item.

If a special pass structure is provided as the result of a safety analysis, cost charges will be determined by each individual situation.

If a design change requires the alteration of a pass structure after completion of negotiations, when a fixed amount has been established and paid by others, any added cost of the structure will be borne by TxDOT as a construction item.