Section 5: Environmental Clearance

Anchor: #i999681

Process

Before authorization, the project must have environmental clearance by approval of a Final Environmental Impact Statement, Environmental Assessment (EA), Categorical Exclusion (CE), Finding of No Significant Impact (FONSI), or Record of Decision (ROD) or concurrence that it is a non-major action project. This clearance is obtained through the Environmental Affairs Division, Environmental Compliance Oversight System (ECOS). For more information on these clearances, refer to the TxDOT environmental procedures in the Project Development Process Manual.