Section 4: Contract Time

Anchor: #i1025613

Beginning Time Charges

Time charges begin within 30 calendar days after the Authorization to Begin Work. Unless otherwise shown in the contract, the contractor has the option to begin work any time within the 30 calendar days after.

In some cases, the contract will include a provision to allow for extending the beginning of time charges on the contract beyond the standard 30 calendar days. When the contract includes a delayed start time provision, act in accordance with the contract provisions.

For contracts with work orders, such as a traffic signal project, begin working day charges as established for each individual work order.

Anchor: #i1025638

Computation of Contract Time

In accordance with Article 8.3.1, “Working Day Charges,” of the Standard Specifications, assume time is to be charged based upon the standard workweek method unless otherwise specified in the contract (General Notes, Item 8). Other possible methods include the following.

Do not suspend working day charges without suspending work, wholly or in part.

For five-, six- or, seven-day workweek and calendar-day contracts, do not consider weather conditions or materials availability when suspending working day charges.

Do not suspend working day charges or grant additional contract working days for activities relating to handling hazardous material delivered by the Contractor.

Consider adjusting the number of contract working days by change order under extraordinary circumstances. When reducing scope on a project, reduction in working days may be discussed.

Work on Sundays must be requested for all projects except calendar-day and seven-day workweek projects.

For standard workweek contracts, do not allow the Contractor to perform work on national or state holidays unless requested in writing. Email is acceptable. State Holidays authorized by State Legislature are Martin Luther King, Jr. Day, Confederate Heroes Day, Presidents’ Day, Texas Independence Day, San Jacinto Day, Emancipation Day, LBJ Day, Veterans Day, Day After Thanksgiving, Christmas Eve and Day After Christmas.

For five-, six- or, seven-day workweek contracts, do not allow the Contractor to perform work on national holidays unless requested in writing. Email is acceptable. National holidays are January 1, the last Monday in May, July 4, the first Monday in September, the fourth Thursday in November, and December 24 or December 25.

Provide written authorization to the Contractor if work will be allowed on a state or national holiday.