Section 5: Project Closeout
Anchor: #i1057639Overview
Project Closeout is the process of collecting all of the paperwork required to be submitted over the life of the project, to support pay quantities and to support the decisions made during the life of the project. The information contained in this documentation may be needed in the future if a claim or lawsuit is filed. The project closeout is a two-step process, beginning with project record keepers in the Area Office (AO) and finished by the District Construction Office (DCO). Close out a project within 60 days from final acceptance.
The following checklist was created to assist the AOs and may not be all-inclusive. Individual projects may include additional items. Review the available project information, including the plans, specifications, and special provisions.
Include all files, tickets, etc. in the project files; do not retain project information in the AO.
Anchor: #i1057712Project Closeout Checklist
- Anchor: #SYEKDNGR
- Project Event List
- A chronological list of all of the major events on the project
-
Anchor: #RWDUQDBD
- Letting Anchor: #INQOEJEU
- Award Anchor: #PBLQRQND
- Execution Anchor: #PRKNWLBK
- Preconstruction Meeting Anchor: #CKAVEQJH
- Preconstruction Safety Meeting Anchor: #WGHEAGOP
- Work Begin Anchor: #JIJXHPDC
- Time Suspensions Anchor: #RQJKJNYF
- Milestone Dates Anchor: #LDIKCNUW
- Substantial Completion Anchor: #QKMNWRCI
- Project Acceptance Anchor: #CVLRVDQQ
- Final Estimate Anchor: #LYYMALUL
- Other important dates
Anchor: #AJWFJHLV - Preconstruction Contract Correspondence Anchor: #TPTVLVOL
- Contract Anchor: #JIKWWCAP
- Bid Tabulations Anchor: #UWEPGCWU
- Utility or ROW Conflicts Anchor: #USKRHDFS
- Railroad Right of Entry (ROE)
-
Anchor: #PISNARYL
- Railroad insurance information
Anchor: #KKLHMDVP - Preconstruction Meeting Notes, Sign-In Sheets, etc. Anchor: #QFHVHRTB
- Partnering Meeting, Invoice, etc. Anchor: #IQEQOGKD
- Preconstruction Safety Meeting Notes Anchor: #WUJWVNBM
- DBE/SBE Subcontractors
-
Anchor: #DJIGGRDA
- Subcontract Agreements Anchor: #DATYMANE
- Purchase Orders Anchor: #HQBFHAKY
- Monthly/Final Payouts Anchor: #NWUQKNNL
- Completed CUFs Anchor: #PULGOYXB
- Goal Shortfall Explanations and Analysis if applicable.
Anchor: #LMOQOIHM - Subcontractor Approval (Form 2802 Contractor Request for Sub Approval for projects let May 2020) Anchor: #XTEJXPIE
- Monthly/Final Prompt Payment certification Anchor: #WSBGNTME
- Prompt Pay Audits (Form 2177A) Anchor: #UJEFFTCP
- Project Schedule
-
Anchor: #AAPUTMDD
- Baseline Schedule Anchor: #CANORDRI
- Monthly Updates Anchor: #QYLWTHTQ
- Notice of Potential Time Impact Anchor: #HRVCQIRU
- Time Impact Analysis
Anchor: #LTXAGEKN - Materials
- Anchor: #DAIKSPMC
- Sources Anchor: #AIPYLEFM
- Materials Lists Anchor: #IBPWRVSG
- Tickets Anchor: #UQYEWVUG
- Materials Test Documentation/Deficiencies Anchor: #UYJIEUTQ
- Product Data Sheets Anchor: #DIUHKXFQ
- Requests for Material on Hand (MOH) Anchor: #VXMFQHLN
- Materials Invoices Anchor: #TOOGKJOR
- Lab Invoices Anchor: #JSWJVYVU
- Testing Employee and Lab Certifications Anchor: #WEUEFJBC
- Manufacturers’ Literature Anchor: #JRWDVDFJ
- Mix Designs Anchor: #IJQOPDQU
- Certified Test Reports Anchor: #KSFMVAFB
- Quality Control Plans Anchor: #CCIIQQKW
- Joint Density Test Results Anchor: #MKWJPUCF
- Seed Mix Certifications Anchor: #DUVVEOYK
- Materials Certification Letter (MCL) Anchor: #TCKVTFHL
- Test Exception Letter (TEL) (if applicable)
Anchor: #JLCXRQAO - Construction
- Anchor: #OAAVYQOH
- Bulletin Board Compliance Anchor: #LXIGGOKO
- Asphalt Pavement Records
-
Anchor: #HIBDSAMP
- Seal Coat Records Anchor: #CQJTDKTB
- Asphalt Anchor: #XIHYVOGS
- Aggregate Anchor: #YGDFLHFP
- ACP Records
Anchor: #WDDRDFRR - Ride Quality Measurement Records Anchor: #SKMNYOJO
- Concrete Pavement Paving and Quality Control Plan Anchor: #IQOKMYEG
- Flowable Fill Construction Method and Plan Anchor: #JCAIGCGJ
- Temporary Special Shoring Details Anchor: #AGGXPHYO
- Pile Driving Erection Plans Anchor: #KFJSQPQL
- Pile Jetting Plans Anchor: #YXMNGSRS
- Pile Bearing Evaluation Document
-
Anchor: #URARORNW
- Pile Driving Records and updated Bridge Layouts showing actual foundation tip elevations, provide to the district bridge office to be included in the bridge file in the bridge inspection management system (currently AssetWise)
Anchor: #RSQRFXWF - Soil Nail Wall Construction Plans Anchor: #PUDQDGHX
- Drilled Shaft Installation Plan
-
Anchor: #CRYXBDXB
- Drill Shaft Records and updated Bridge Layouts showing actual foundation tip elevations, provide to the district bridge office to be included in the bridge file in the bridge inspection management system (currently AssetWise)
Anchor: #KYGIRCUB - Freeze Protection Measures Anchor: #PETRBBHD
- Plans for Falsework and Forms Anchor: #ODAGBEIE
- Bridge Paint Containment Plans Anchor: #QBCBXUSU
- Special Concrete Finish Plans Anchor: #FBIQPDPP
- Work Plans Anchor: #QUDSTNAJ
- Technical Support Representatives Anchor: #LRIVAHQA
- Welding Procedures Anchor: #FOQSXKXM
- Certificate of Conformance Anchor: #BAYDHACA
- Shop Drawings/Working Drawings Anchor: #KQSNRTWV
- Erection Drawings Anchor: #DJXROHYA
- Nonconformance Reports Anchor: #MEWDAUXQ
- Demolition Plans Anchor: #JUXQLICN
- SWP3 Training List Anchor: #IKJAVRFE
- Herbicide Records
Anchor: #GPJOOCED - Equipment Verifications Anchor: #LTFBYBCV
- DWRs - make sure all DWRs in SiteManager have been authorized Anchor: #POOVIUWV
- Monthly Estimates
-
Anchor: #JQXOYWRQ
- Check percentage of work performed by prime and subs Anchor: #ILKQKWYE
- Check major items for over/underrun greater than 25%
Anchor: #JBYBPNUB - COs, Force Account, etc. - All correspondence and approved or unapproved COs Anchor: #MWUHAOQX
- Dispute Correspondence, Requests for additional compensation, etc., – approvals, denials Anchor: #NUKXIMSA
- Traffic Control Plans, Revisions, Contractor
Proposed Changes, etc.
- Anchor: #FJXLPAQJ
- Paper copies
of Form 599, “Traffic Control Devices Inspection Report”
-
Anchor: #ULIRGFGM
- Barricade Folder includes all 599s performed
Anchor: #NRWIKLHT - The 599 folder is separate from the project files, labeled with “DO NOT DISCLOSE - EXCEPTED FROM DISCLOSURE BY 23 USC §407.” This file is considered safety information that federal law exempts from discovery, which makes them exempt from disclosure under the Public Information Act
Anchor: #QKHLYGKH - Paper copies
of Form 599, “Traffic Control Devices Inspection Report”
- Environmental Compliance
-
Anchor: #VXRVAKEU
- SWP3 Documentation Anchor: #BYNYMKFV
- BMPs Anchor: #UFGSNSPF
- Construction Stage Gate Checklist Anchor: #XOWBXEUT
- Other Environmental Commitment Documentation as required
Anchor: #DVBEDHEU - Buy America/Buy Texas Documentation Anchor: #QRCECYJL
- Overweight Construction Traffic Submittals and Approvals Anchor: #EXHSFJIH
- Construction Equipment Operating on Structures or Materials Stored on Structures Plans and Approvals Anchor: #IPYGBKKY
- Employee Certifications
-
Anchor: #HYVSISRG
- Flaggers (if requested) Anchor: #UHMEEGKI
- Electricians Anchor: #QIKQGWQO
- Irrigators Anchor: #AEMHGSAU
- Profilers
Anchor: #WJUJTDQG - Labor Compliance
-
Anchor: #PWGCSSHV
- Payroll hard copies ( Form WH-347) if not submitted to the Engineer in the manner prescribed by the Department Anchor: #WNEBELAE
- Labor Interviews Anchor: #DNNRLPFA
- OJT
Anchor: #GUQJTGEC - Incident and Injury Reporting (for projects
let before September 2020 in which SP 000-010 was not removed by
change order)
- Anchor: #OMUTRGXX
- Check EPRS to ensure contractor has submitted incidents and injuries that have occurred on the project. These should correspond to information in the DWRs.
Anchor: #FNWXXQEE - Other Correspondence Anchor: #BVTYJTGF
- Disposal of Wells Plugging Report Anchor: #EUMXJMJM
- As Built Plans Anchor: #OWEOKWDN
- Statement of Cost (SOC) (if applicable) Anchor: #DYDYGSNK
- Final hard copy Contractor Performance Evaluation Form 2707, Form 2707R and complete backup documentation saved in a folder separate from the project files, labeled “DO NOT DISCLOSE - Attorney General Opinion Required.” Anchor: #UBQIKIWU
- Form 2803 Project Evaluations (Design) - Required for all Final Estimates processed after NOV 2022 Anchor: #KCYEGRCF
- District project review(s).