Appendix B: Project Classifications
Anchor: #i1005664Introduction
This section lists project classifications found in TACS table DCSPRCLS Notes, including their code and their primary function of CSJ.
Code |
Classification |
Notes: Primary Function of CSJ will be: |
---|---|---|
PE |
Preliminary Engineering |
Preliminary engineering only |
BR |
Bridge Replacement |
Replacement of structure on existing location |
BWR |
Bridge Widening Or Rehabilitation |
Rehabilitation or widening of deck, sub or super structure of an existing bridge to upgrade bridge to loading standards or geometric standards or traffic capacity |
HPR |
Remove Hazardous Paint (Bridge Rehab Projects) |
Removal of hazardous paint on bridge rehabilitation projects |
CNF |
Convert Non-Freeway To Freeway |
Added capacity conversions of multilane highways with non-controlled access to controlled access freeway |
WF |
Widen Freeway |
Added capacity widening of an existing freeway facility |
WNF |
Widen Non-Freeway |
Added capacity widening on an existing non-freeway facility, and addition of travel lanes |
NLF |
New Location Freeway |
A controlled access facility on new location |
NNF |
New Location Non-Freeway |
A non-freeway facility on new location |
INC |
Interchange (New or Reconstructed) |
A complete interchange facility (such as trumpet, diamond, three-level diamond, cloverleaf, partial cloverleaf, or directional) on new location or reconstruction of interchange on existing right of way |
SC |
Seal Coat |
Surface treatment of one or more applications of asphalt covered with aggregate for sealing of existing pavements |
OV |
Overlay |
Leveling up or surfacing a pavement course, or any combination composed of a compacted mixture of mineral aggregate and asphaltic material |
RES |
Restoration |
Restoration of pavement structure to existing configuration to meet 2R standards as a minimum. This function may include some minor safety upgrading. |
RER |
Rehabilitation of Existing Road |
Reshaping and/or addition of existing base courses, including resurfacing, within existing right of way to meet 3R Standards. This function includes (but not limited to) minor safety upgrading, such as widening culverts and guard fence. |
UPG |
Upgrade to Standards Freeway |
Upgrading of a freeway facility to full current geometric standards including base or pavement support enhancements |
UGN |
Upgrade to Standards Non-Freeway |
Upgrading of a non-freeway facility to current geometric standards including base or pavement support enhancements |
Code |
Classification |
Notes: Primary Function of CSJ will be: |
MSC |
Miscellaneous Construction |
Miscellaneous construction that provides for driver assistance in travel. For example: signing, pavement markings, illumination, adding turn lanes, adding or moving entrance or exit ramps (usually small projects) |
LSE |
Landscape and Scenic Enhancement |
Improvements of overall aesthetics of right of way or enhancement of roadside view |
TS |
Traffic Signal |
New traffic signal, or upgrade of signalized intersection |
HES |
Hazard Elimination & Safety |
All projects of federal traffic safety program |
CTM |
Corridor Traffic Management |
Corridor traffic management systems |
GCP |
Grade Crossing Protection |
Signalization and/or controls for grade crossing protection |
TPD |
Traffic Protection Devices |
Traffic protection devices |
FS |
Feasibility Studies |
Preliminary investigations, data collection, study of alternatives, costs, benefits, etc., and recommendations |
ROW |
Right of Way |
The purchase of right of way |
UTL |
Utility Adjustments |
The adjustment of utilities |
JC |
Junkyard Control |
Junkyard control measures |
OAC |
Outdoor Advertising Control |
Outdoor advertising control measures |
SRA |
Safety Rest Area |
Construction of safety rest area |
FBO |
Ferry Boat |
The construction of landings, approaches, or appurtenances to ferry boat operations |
TC |
Tunnel Construction |
Construction of tunnels |
RR |
Railroad Relocation |
Relocation of railroads |
SKP |
SKIP (Exempt from sealing – Transportation Enhancement Project |
Projects where the plans are exempt from sealing and dating requirements (no professional engineer's seal) |
BCF |
Border Crossing Facility |
Construction of Border Crossing Facility |
Project Classifications Used in the LAR
This section lists project classifications used in preparing the Legislative Appropriation Request (LAR). The performance measure reports of LAR retrieve information from the project evaluation screen (P3). Information regarding each project’s existing and proposed facility must be complete in order to accurately report department activities to the Texas Legislature. The following project classifications must have an existing and proposed facility information shown on the project evaluation screen.
Code |
Description |
Required Entry |
---|---|---|
BR |
Bridge replacement |
Existing facility |
BWR |
Bridge widening or rehabilitation |
Existing and proposed facility |
CNF |
Convert non-freeway to freeway |
Existing and proposed facility |
WF |
Widen freeway |
Existing and proposed facility |
WNF |
Widen non-freeway |
Existing and proposed facility |
NLF |
New location freeway (only proposed facility information) |
Existing and proposed facility |
INC |
Interchange (new or reconstructed) |
Existing and proposed facility |
SC |
Seal Coat |
Existing and proposed facility |
OV |
Overlay |
Existing facility |
RES |
Restoration of existing road |
Existing facility |
RER |
Rehabilitation of existing road |
Existing facility |
UPG |
Upgrade to standards freeway |
Existing facility |
UGN |
Upgrade to standards non-freeway |
Existing facility |